Supply and Fix Brickwork & Scaffolding Package
Contractor: Balfour Beatty
Project Value : £1.2 million
Programme : 26 weeks

This Package included the Supply and laying of 22N Midi Blockwork to the External perimeter blockwork skin along of the New Ballroom and Hotel

blockwork Partitions throughout the project

Scaffolding and Skyjack access systems both internally and externally